Phase 3 internal roads reach 70% completion
Grading and compaction are finished on the main spine roads, with surface dressing under way. Drainage lines on Streets 1–4 are complete.
70%
Internal roads completed
Phase 3, Abuja
Update summary
What was recorded
As at February 2026, grading and compaction on the Phase 3 main spine roads were complete. Surface dressing was under way, and drainage lines on Streets 1–4 were complete. This is a dated record, not a statement of current completion.
Recorded milestones
The report, at a glance
- 01Main spine road grading and compaction completed
- 02Surface dressing under way at the reporting date
- 03Drainage completed on Streets 1–4
Important context
This report is dated, not live.
Construction progress, availability and prices can change after publication. Request current dated evidence or inspect the site before relying on this record.